- Complete Electrical Upgrade to Existing MDF Plant
- All Electrical on new equipment
- Design/Supply/Install and Commission of New SIemens
- VFD
- CIE was the only Electrical Contractor on site for the project
- Install Multiple Fire detection and suppression systems
- Control Upgrades
- Electrical Install of new MDF Forming Line
- Electrical Install of 6 new baghouses
- Install and terminations of new Fibre Optic Network